"New energy" blows out the new future of "old tuyere"

Editor’s Note: The year 2024 marks the 75th anniversary of the founding of New China, and it is a crucial year to realize the objectives and tasks of the 14th Five-Year Plan. In order to fully demonstrate that Xinjiang insists on high-quality development as the last word in the new era and strive to create a new situation of reform, development and stability in Xinjiang, Xinjiang Channel of Yangguang. com, together with the Network Information Office of Xinjiang Uygur Autonomous Region Party Committee and State Taxation Administration of The People’s Republic of China Xinjiang Uygur Autonomous Region Taxation Bureau, planned and launched the network theme communication activity of "High-quality development sees Xinjiang’s" new quality and new creation ",and sent reporters to focus on the construction of" eight industrial clusters "in Xinjiang to present Xinjiang’s new industries, new models, new kinetic energy and new achievements in a three-dimensional way.

On May 22nd, a reporter from Tory County, Tacheng District, Xinjiang went to emin county on National Highway 335, and saw rows of white fans arranged neatly on both sides, which became a landscape in Tory County. The snow-capped mountains and fans in the distance set each other off, weaving a green song of nature.

Toli County in Tacheng area has two strong wind areas, namely Laofengkou-Mayitas and Hejiaoke-Tieleketi, with long sunshine time in the same period. Tacheng area is fully promoting the large-scale and intensive development of new energy industry around the requirements of the construction of "eight industrial clusters" in the autonomous region. In the first quarter of this year, the total installed capacity of new energy was 4.3732 million kilowatts, and the power generation was 1.471 billion kWh.

The snow-capped mountains in the distance are in contrast with the fans (photo by Guo Yuyue, a reporter from Yangguang. com)

At Huaneng Laofengkou Wind Farm, director Zhang Tong told reporters that Huaneng Tacheng Laofengkou Wind Power Project has installed eight wind turbines with a single unit capacity of 6.25 MW, which can provide 136 million kWh of clean electricity for the power grid every year, saving about 41,400 tons of standard coal every year compared with coal-fired power plants.

"We are the first mountain wind farm of Huaneng Qingneng Company, which can provide one-sixth of the electricity consumption of Tory County. At present, there are five staff members in the station, and only daily maintenance and overhaul are needed. " Zhang Tongfang said.

The director of Huaneng Tori Wind Power Co., Ltd. Tori Wind Farm introduced the power generation situation to the reporter (photo by Guo Yuyue, reporter of Yangguang. com)

Corner of Huaneng Laofengkou Wind Farm (photo by Daerhan from Yangguang. com)

Not far from Huaneng Laofengkou Wind Farm, the 100,000 kW wind power project supporting Datang Laofengkou 25,000 kW/100,000 kWh energy storage project is under construction, and efforts are made to connect the grid with full capacity to generate electricity in August, turning wind power into electricity and delivering it to thousands of households.

"We plan to build 12 8.35 MW wind turbines. At present, the wind turbines with the largest single capacity in Xinjiang are under construction. After completion, the annual power generation will be about 260 million kWh." Han Zhiwei, project manager of Tacheng Wind Farm of Datang Xinjiang Power Generation Co., Ltd. said.

Project construction site (photo by Yang Guangwang reporter Guo Yuyue)

In order to speed up the construction progress of the project, Tacheng has set up a special service class to track the whole process of service construction projects. At present, there are 6 new energy projects under construction in Toli County with an installed capacity of 3.6 million kilowatts.

Han Zhiwei, project manager of Tacheng Wind Farm of Datang Xinjiang Power Generation Co., Ltd., said: "Tacheng area has given strong support to our land use procedures, forest and grass procedures and environmental protection procedures, and leaders at all levels often go to the site to investigate and guide related work, understand the situation on our site, specifically where we encounter difficulties and bottlenecks, and then communicate and solve the actual problems we encounter on the spot to escort our project."

Wind power facilities in the sun (photo by Yang Guangwang from wangxin)

In the past, the "old tuyere" with frequent wind disasters has taken on a new look. Now, the wind of the "old tuyere" has become a new resource in Tori County, contributing to the development of new energy. Up to now, Toli County has built 830,000 kilowatts of new energy for grid-connected power generation, 3.6 million kilowatts of projects under construction and 4.43 million kilowatts of new energy. In February this year, wind power enterprises in Toli County generated 227 million kWh of electricity, up 9.8% from the previous month, and generated 423 million kWh of green electricity annually.

Toli County adheres to the development layout around the "eight industrial clusters" in Xinjiang and the "three economic sectors" in Tacheng area. The planned installed capacity of the wind area is 15.6 million kilowatts, covering an area of 3,712.08 square kilometers. "We should give full play to the leading role of local governments, mobilize the enthusiasm of investors, and promote the high-quality development of wind power and photovoltaic power generation, and strive to reach 5 million kilowatts of installed capacity of new energy by the end of the 14 th Five-Year Plan." Zhao Jing, head of the new energy industry department in Tori County, said.

Coordinator: Hu Miaomiao and Yu Pengtao